Shutdown Requirements
What to include in your MDAD Shut‑Down Request Package
- Site plans or as‑builts showing affected areas
- Scope of work
- Panel schedule, etc.
- Water: Site plans/as‑builts showing affected areas; scope of work
- Sewer: Site plans/as‑builts showing affected areas; scope of work; environmental action plan (if required)
- Site plans/as‑builts showing affected areas; scope of work
- Copies of permits and licenses
- Copies of Honeywell plans (and Honeywell Shutdown Notice)
- Site plans/as‑builts showing affected areas; scope of work
- Copies of permits and licenses
- Copies of Honeywell Security Plan, Matrix, BlackBox, and Honeywell concurrence letters of walk‑through involvement
For shutdowns affecting life-safety‑related systems, plans must indicate and label the affected
nested zones of fire alarm, paging, fire suppression and/or smoke management systems and components.
Submit the completed package at least 14 calendar days before the requested shutdown date to allow full coordination.
- Planos de sitio o as‑built con áreas afectadas
- Alcance del trabajo
- “Panel schedule”, etc.
- Agua: Planos/as‑built con áreas afectadas; alcance del trabajo
- Alcantarillado: Planos/as‑built; alcance del trabajo; plan de acción ambiental (si aplica)
- Planos/as‑built; alcance del trabajo
- Copias de permisos y licencias
- Copias de los planes de Honeywell (y aviso de shutdown de Honeywell)
- Planos/as‑built; alcance del trabajo
- Copias de permisos y licencias
- Copias del Honeywell Security Plan, Matrix, BlackBox y cartas de conformidad de Honeywell por “walk‑through”
Para shutdowns que afectan sistemas de life safety, los planos deben indicar y etiquetar las zonas
“nested” afectadas de alarma de incendio, “paging”, supresión de incendios y/o manejo de humo.
Envíe el paquete completo con al menos 14 días de anticipación a la fecha solicitada.